The following guidance outlines the key issues that should be considered when approaching a dispute in relation to a PPP contract using some select common dispute resolution mechanisms.
Disputes can be created by issues associated with complex contractual terms including the agreed risk allocation between the parties, claims for compensation or additional time, application of payment deductions, Procuring Authority obligations and other procedures and defined time requirements. These issues can be exaggerated where the parties do not have a strong fundamental understanding of PPPs and the specific terms of the relevant PPP contract. Having a strong fundamental understanding of the agreement between the parties is essential.
The Procuring Authority should be aware of the legal frameworks that govern the relationship between it and the Project Company. There may be legal principles in both civil law and common law jurisdictions that are relevant to what is otherwise agreed between the parties in the PPP contract. A specific example of this is the obligations of a regulator acting as a Procuring Authority. This has been a difficult issue in the energy sector where the level of discretion granted to the regulator in the setting of tariffs has caused issues to Project Companies. The Procuring Authority should be aware of all its obligations under the PPP contract and under the applicable laws.
Strict and unfair enforcement of contractual provisions can also lead to disputes. For example, a strict reading of PPP contracts as they relate to claims and payment deductions. A claim can refer to a claim for compensation or additional time. Management of clams is detailed in Section 3.5 (Claims). A Procuring Authority will retain some risk under a PPP contract. The Procuring Authority may create larger issues for a project if it draws out and fails to manage appropriately any claim with respect to those risks.
Payment mechanisms and deductions are typically linked to performance and agreed during the procurement phase. Payment deductions should be applied as was agreed in the PPP contract. Performance monitoring and the application of payment deductions detailed in detail in Section 3.2 (Performance monitoring).
The Procuring Authority should use payment mechanisms and deductions to incentivise the Project Company to perform in an appropriate manner. An issue can arise if there is an unnecessarily strict enforcement of payment deductions in an inconsistent or unfair manner. For example, the Procuring Authority may be tempted to strictly apply a payment deduction against the Project Company with an unrelated goal in mind, perhaps to create leverage to resolve a wider dispute.
As well as being caused by the action of the Project Company, a project can also be negatively affected by the actions of a Procuring Authority. A Procuring Authority managing its budget deficits may be incentivised to apply payment deductions in a very strict manner. For example, this subject arose in interviews in the UK where local authorities had had their budgets cut and were perceived by the private sector to be under pressure to interpret all obligations and performance standards very strictly.
In some jurisdictions this behaviour may fall foul of general legal obligations to act in good faith. In addition, such behaviour risks damaging the relationship between the parties, and increasing the costs of disputes, which will have a harmful effect on the project in the longer term.
The Procuring Authority may decide that certain procedures are unworkable and that it will formally waive or amend the unworkable contractual requirements and agree to a less formal and more workable process. Waiving rights under a contract should only be undertaken after receiving legal advice, to ensure an appropriate waiver is effected (i.e. that the Procuring Authority is waiving only what it is intending to waive and not waiving any other rights under the PPP contract).
Key advantages
Key disadvantages
Key advantages
Key disadvantages
Key advantages
Key disadvantage
Key advantage
Key disadvantage
Key advantage
Key disadvantages
Key advantages
Key disadvantages
Attachment: Dispute negotiation checklist
View our list of previous questions and answers or submit a question to our PPP Contract Management team.